Massachusetts budget approval allows utilities to recoup added cost of hydropower corridor
Johnathan Walker View
Date:2025-03-11 04:15:31
PORTLAND, Maine (AP) — A budget signed by Massachusetts Gov. Maura Healey this week will allow utilities to raise rates to make up for hundreds of millions of dollars in additional costs to complete a transmission line to bring Canadian hydropower to the New England electricity grid.
The head of Central Maine Power Co.'s corporate parent Avangrid has said the cost of the $1 billion project grew to $1.5 billion as litigation delayed construction and inflation caused prices to creep upward.
Legislation included the supplemental budget adopted Monday allows transmission service agreements to be renegotiated and additional costs to be passed along to Massachusetts ratepayers to cover the added costs.
Avangrid provided the increased costs to Massachusetts’ electricity distribution companies to adjust the rate in the parties’ transmission services agreements, which would be subject to Department of Public Utilities review and approval, Avangrid spokesperson Leo Rosales said in a statement Tuesday.
He praised Healey and lawmakers for taking action to “deliver this critical project and needed clean power to benefit the entire New England region.”
Avangrid partnered with Hydro-Quebec on the New England Clean Energy Connect to supply 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That would be enough electricity to power about a million homes.
The 145-mile (233-kilometer) transmission line will stretch from Lewiston, Maine, to the Canadian border.
It received all regulatory approvals but was plagued by delays, litigation and a referendum in which https://apnews.com/article/election-2021-maine-hydropower-line-54dea1a948e9fc57a667280707cddeb7
It was allowed to move forward after a Maine jury concluded that the developers had a constitutional right to proceed despite the referendum.
Construction resumed in August on a transmission hub that’s critical to the project in Lewiston. But it’s unclear when other work will restart.
Workers had already begun removing trees and setting utility poles on a disputed portion of the project, a new 53-mile (85-kilometer) section cut through the woods in western Maine, before the project was put on hold.
The project was envisioned to meet Massachusetts’ clean energy goals, and the cost is fully borne by ratepayers in that state.
However, supporters say electricity would lower energy costs across New England as well as reduce carbon pollution.
veryGood! (515)
Related
- South Korea's acting president moves to reassure allies, calm markets after Yoon impeachment
- Rudy Giuliani should be disbarred for false election fraud claims, D.C. review panel says
- Greenhouse Gas Emissions Plunge in Response to Coronavirus Pandemic
- Kelly Clarkson Shares How Her Ego Affected Brandon Blackstock Divorce
- NHL in ASL returns, delivering American Sign Language analysis for Deaf community at Winter Classic
- Climate Change is Weakening the Ocean Currents That Shape Weather on Both Sides of the Atlantic
- These Candidates Vow to Leave Fossil Fuel Reserves in the Ground, a 180° Turn from Trump
- Louisiana’s Governor Vetoes Bill That Would Have Imposed Harsh Penalties for Trespassing on Industrial Land
- Newly elected West Virginia lawmaker arrested and accused of making terroristic threats
- Get a $64 Lululemon Tank for $19, $64 Shorts for $29, $119 Pants for $59 and More Mind-Blowing Finds
Ranking
- Costco membership growth 'robust,' even amid fee increase: What to know about earnings release
- Why the proposed TikTok ban is more about politics than privacy, according to experts
- Vermont Doubles Down on Wood Burning, with Consequences for Climate and Health
- Why the proposed TikTok ban is more about politics than privacy, according to experts
- Kylie Jenner Shows Off Sweet Notes From Nieces Dream Kardashian & Chicago West
- Connecticut Passed an Environmental Justice Law 12 Years Ago, but Not That Much Has Changed
- Was your flight to Europe delayed? You might be owed up to $700.
- Tree Deaths in Urban Settings Are Linked to Leaks from Natural Gas Pipelines Below Streets
Recommendation
Why we love Bear Pond Books, a ski town bookstore with a French bulldog 'Staff Pup'
Michael Cohen plans to call Donald Trump Jr. as a witness in trial over legal fees
Warming Trends: A Baby Ferret May Save a Species, Providence, R.I. is Listed as Endangered, and Fish as a Carbon Sink
Larsa Pippen and Marcus Jordan Respond to Criticism of Their 16-Year Age Gap
See you latte: Starbucks plans to cut 30% of its menu
Cities Pressure TVA to Boost Renewable Energy as Memphis Weighs Breaking Away
How 2% became the target for inflation
Residents Want a Stake in Wisconsin’s Clean Energy Transition